  • Person - retrieve the number of hours already entered in CATS for the technician on a given day and add this number to the length of time effort. Compare the overall number with the allowed duration time. If the number is exceeded, split the time effort into two parts - the first one lasting the amount of entered duration time, the second one will be all the time left.

  • Order - retrieve the number of hours already entered in CATS for the technician AND THE SERVICE ORDER on a given day and add this number to the length of time effort. Compare the overall number with the allowed duration time. If the number is exceeded, split the time effort into two parts - the first one lasting the amount of entered duration time, the second one will be all the time left.

  • Empty - duration time is not considered

...

The following time splitting entries are maintained for plant 1200, source activity type 101 and weekday Wednesday:

...

The time posting was split into two - effort fits into three duration time frames (the first three hours into the first one lasting the duration of the first customizing entry (3 hours), and the second one lasting the rest.

...

, the next 5 hours into the second one and the last 11 hours into the last one), therefore the posting will be split into three CATS entries, each with different activity type and Attendance/absence type:

...

The actual start/finish times in the customizing entry didn’t influence the time splitting in this case.

...