Holiday calendar assignments follow the rules presented on the diagram below:

...

Use work center for holiday calendar determination

Status
titleADD-ON 200 SP04

Starting from add-on 200, SP04, apart from Personnel Subareas and Plants, calendar assignments can be determined also based on work center’s calendar:

...

Assignment of a technician to a holiday calendar will be determined based on their work center’s factory calendar’s holiday calendar. Holiday calendar assignments are sent:

  • only for active and plannable FSM-relevant technicians (maintained in transaction /PACG/ECM_MAINT_USER) whose work centers belong to the plant assigned to object ‘HOLIDAYCALENDAR’ for a given company

  • if in transaction /PACG/ECM_HCAL - Holiday calendar customizing, field Cal Source is set to ‘Work center’.

 

To use work centers as an additional filter in the sending transaction, enter a company ID and press enter:

...