Activity 

SAP → FSM

FSM property

Source in SAP ECC/S4

Planned start date

If ‘DT Order Header’ set in transaction /PACG/ECM_SCTD, basic dates from service order header are used. Otherwise, operation constraints are used. If constraints cannot be found, field ‘Assignment date/time’ from /PACG/ECM_SCTD determines the date source.

  • Early – use earliest scheduled start date/time

  • Late – use latest scheduled start date/time

  • Early and late – use earliest scheduled start date/time

Planned end date

If field ‘DT Order Header’ is set in transaction /PACG/ECM_SCTD, basic dates from service order header are used. Otherwise, operation constraints are used. If constraints cannot be found, field ‘Assignment date/time’ from /PACG/ECM_SCTD determines the date source.

  • Early – use earliest scheduled finish date/time

  • Late – use latest scheduled finish date/time

  • Early and late – use latest scheduled finish date/time

Duration / Original Estimate

Operation duration

Planned duration

Operation’s work

Earliest start date

Based on setting ‘Dates alloc’ in transaction /PACG/ECM_SCTD:

Image Modified

  • B - basic dates - Basic start date from Service Order Header

Image Modified

  • S (space, default value) - scheduled dates – use earliest scheduled start date from the operation

Image Modified

Due date

Based on setting ‘Dates alloc’ in transaction /PACG/ECM_SCTD:

  • B - basic dates, use service order header basic finish date

Image Modified

  • S (space, default value) - scheduled dates – use latest scheduled finish date from operation

Image Modified

 

FSM → SAP

FSM property

Target in SAP ECC/S4

Planned start

Operation constraint start date (Earliest start/Latest start also updated)

Image Modified

Planned end

Operation constraint finish date (Earliest finish/latest finish also updated)

Duration

Duration updated only if ‘No work/dur’ not set in transaction /PACG/ECM_SCTD; Operation duration normal

Planned duration

Operation work activity

Earliest start date

No impact 

Due date

No impact

 

Service call

SAP → FSM

FSM property

Source in SAP ECC/S4

Start date

Based on setting ‘Dates alloc’ in transaction /PACG/ECM_SCTD:

  • B - basic dates - Bsc start from Service Call Header is used:

Image Modified

  • S (space, default value) - scheduled dates - the Earl start from the earliest operation is set as Start date:

Image ModifiedImage ModifiedImage Modified

End date

Based on setting ‘Dates alloc’ in transaction /PACG/ECM_SCTD:

  • B - basic dates - Basic fin. from Service Call Header is used

  • S (space, default value) - Latest fin from the last operation is used.

Due date

Use the finish date from service order header:

Image Modified

 

FSM → SAP

FSM property

Target in SAP ECC/S4

Start date

Service order headed basic start

End date

Service order headed basic finish, but only if the due date was not maintained in FSM

Due date

Service order headed basic finish - priority over end date if both were maintained in FSM