FSM Connector is now capable of calculating an arrival date for reserved materials and then sending an update to the FSM. To achieve that a new report was created  /PACG/ECM_RMAT_ARRIVAL (transaction /PACG/ECM_RMAT_ARRIV - Reserved Material - arrival date ).

Note

The Arrival Date is also determined automatically right after reserved material creation however the logic behind its determination is very simplified - requirement date for component is used. Proper, scenario-dependent dates are determined after executing program /PACG/ECM_RMAT_ARRIV - Reserved Material - arrival date, which should be scheduled as a regular job.

This report can take following parameters:

...