Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

In the SRS configuration, maintain the colors against the SRS User status.

Image RemovedImage Added

User status color determination


The demands having the column “Work Completed” set to C are considered by the planning procedure as already completed. When rescheduling, they are intended to be frozen (not rescheduled).

Example:

SRS Order has been created and allocated. Two demands have been created: demand #1 and demand #2.

The VSS Order and two corresponding jobs—job #1 and job #2—have been created.

The “Time Book Confirm” event for job #1 has been executed.

Demand #1's demand status is updated. For example, the status BOWC can be set (having “Work Completed = C”). Once the BOWC status is reached, this demand is not subject to further rescheduling.

The approved field work is used by the dispatch monitor application.


Image Added

Business Object User status (2)

Change Demands Allocation 

...