The Arrival Date is also determined automatically right after reserved material creation however the logic behind its determination is very simplified - requirement date for component is used. Proper, scenario-dependent dates are determined after executing program https:/PACG/ECM_RMAT_ARRIV - Reserved Material - arrival dateproaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/1722679297, which should be scheduled as a regular job. |
...
SD Process – Consignation fill-up
Schedule lines are considered and ‘delivery date’ is picked up. In case of multiple schedule lines, the latest (worst) delivery date is considered
...
If a delivery document exists and its Planned Goods Issue date is lower or equal than the delivery date from schedule lines, this date will be taken instead.
...
Expand | ||
---|---|---|
| ||
MATERIAL 1 has quantity 10: ARRIVAL date comes from schedule lines in consignment order.
In the order, there are 3 schedule lines for this material:
As ARRIVAL date, ‘the latest’ date from those schedule lines will be taken, because full quantity 10 PC will be available on 03.03.2023 (partial quantity is available before, but full quantity on 03.03.2023). |
Info | ||||
---|---|---|---|---|
Arrival date used to be displayed only for reserved materials before goods issue for delivery. However, the time between goods movement and arrival to the customer can take longer.
|
...
...
proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/1722679297 if schedule lines change. |
Reservation on ‘VAN stock’
Requested delivery date is retrieved
...