The Resource is a DBM|E specific object. The resource can be defined in DBM|E Service Resource Scheduling or transferred from the SAP HCM.


  • Transfer/Create the resources from HR.


Run transaction /DBME/WMA_SYNC_HR to create/transfer and update the resources from the SAP HCM  system.

The program offers the following functionalities:

  1. Create / Transfer an SRS resource from HR:

1.1 The SRS resources would  be created as follows:


Image Added

Image Added

Image Added

1.2 The SRS resources availability would be created as follows:

Image Added

Image Added


2. Assign Resources to Hierarchy: Assign the created resources to the entered SRS -hierarchy.

Image Added

HR -> SRS sync program


Image Added

Resource Assignment on Hierarchy (Hierarchy Assignment)

3. Create Absences for resources:

Image Added

HR -> SRS sync. program


To transfer the HR absences to the SRS system, the SRS absence types need to be mapped with the HR absence type using the t-code /DBME/WMA_LCM_ABSTP. If no records are found in this transaction, the SRS resource will be created without absences. However, the program will raise an error message in such cases.

Image AddedSRS absence type determination

It is essential to differentiate between HR and SRS absence types. In HR, each absence type can be either full-day or time-limited. However, in the SRS, absence types must be configured as either full-day (All-Day) or time-limited. This is important as All-day and time-limited absence types are treated differently in the capacity calculation in the SRS. Therefore, mapping the HR absence type with the correct SRS absence type is crucial.

Image Added

HR -> SRS sync program log


Image Added

Resource planner -Transfer /Create Absence

4. Update resources:

Image Added

HR -> SRS sync program

4.1 Update the resources when departing: Update the hierarchy assignment valid to date for the inactive resources (Employee status not equal to Active ’3’) based on the HR departure date.


Image AddedHR -> SRS sync program log

4.2 Update the resources working model: The SRS resources' default and availability working models will be updated based on the HR working schedule (0007) and substitutions (2003) info types. This will be done given that there is a mapping between the SRS working model and the HR working schedule rule.

4.3 Update the resource role: If the resource role is not determined during the create resource step (1.2) for any reason, the resource availability can be updated from the update resource step after mapping the resource role with a corresponding position or job key.

Image AddedHR -> SRS sync program log


With the button “New Entries“ a new resource can be created.

...