FSM property

Source in SAP ECC/S4

Planned start date

If DT Order Header’ set in transaction /PACG/ECM_SCTD https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Activity-start%2Fend-from-order-header is set, basic dates from service order header are used. Otherwise, operation constraints are used. If constraints cannot be found, field Assignment date/time’ from /PACG/ECM_SCTD https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Activity-planned-start%2Fend-date determines the date source.

  • Early – use earliest scheduled start date/time

  • Late – use latest scheduled start date/time

  • Early and late – use earliest scheduled start date/time

Planned end date

If field ‘DT Order Header’ is set in transaction /PACG/ECM_SCTD https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Activity-start%2Fend-from-order-header is set, basic dates from service order header are used. Otherwise, operation constraints are used. If constraints cannot be found, field ‘Assignment date/time’ from /PACG/ECM_SCTD https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Activity-planned-start%2Fend-date determines the date source.

  • Early – use earliest scheduled finish date/time

  • Late – use latest scheduled finish date/time

  • Early and late – use latest scheduled finish date/time

Info

The field https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Calculation-of-activity-end-time can overwrite the end date determined based on this option! If set to ‘Add work’ or ‘Add duration’, the end date would be calculated by adding duration or work to the planned start date

Estimated Duration / Original EstimateEstimation

Operation duration

Planned duration

Operation’s work

Earliest start date

Based on setting Dates alloc’ in transaction /PACG/ECM_SCTD:

Image Removed

https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Scall-start%2Fend-and-Act.-earl.start%2Fdue

  • B - basic dates - Basic start date from Service Order Header

  • S (space, default value) - scheduled dates – use earliest scheduled start date from the operation

Due date

Based on setting Dates alloc’ in transaction /PACG/ECM_SCTD: https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Scall-start%2Fend-and-Act.-earl.start%2Fdue

  • B - basic dates, use service order header basic finish date

  • S (space, default value) - scheduled dates – use latest scheduled finish date from operation

...

FSM property

Target in SAP ECC/S4

Planned start

Operation constraint start date (Earliest start/Latest start also updated)

Planned end

Operation constraint finish date (Earliest finish/latest finish also updated)

Duration

Duration updated only if No work/dur’ not set in transaction /PACG/ECM_SCTD https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#No-oper.-work%2Fduration-update-from-FSM not set; Operation duration normal

Planned duration

Operation work activity

Earliest start date

No impact 

Due date

No impact

...

FSM property

Source in SAP ECC/S4

Start date

Based on setting Dates alloc’ in transaction /PACG/ECM_SCTD: https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Scall-start%2Fend-and-Act.-earl.start%2Fdue

  • B - basic dates - Bsc start from Service Call Header is used:

  • S (space, default value) - scheduled dates - the Earl start from the earliest operation is set as Start date:

End date

Based on setting Dates alloc’ in transaction /PACG/ECM_SCTD: https://proaxia-prod-doc.atlassian.net/wiki/spaces/PFCC/pages/2094727169/PACG+ECM+VSCTD+-+Service+Call+types+definition#Scall-start%2Fend-and-Act.-earl.start%2Fdue

  • B - basic dates - Basic fin. from Service Call Header is used

  • S (space, default value) - Latest fin from the last operation is used.

Due date

Use the finish date from service order header:

...