Reserved materials can use project stock. FSM technicians can see not only unplanned project stocks but also the reserved materials from project stock.

 

Prerequisite

Make sure that a project stock is maintained as a special stock in transaction /PACG/ECM_WRHOUSE - FSM warehouse (field ‘WBS element’).

...

The stock should be transferred to FSM.

 

Process overview

A WBS element should be entered in service orders additional data:

...

If consumed on the mobile app, the following Goods movement is performed, with reference to the WBS element and special stock ‘Q’:

...

Prerequisite