Dates for WBS service calls and activities can be customized using fields ‘DT Order Header’, ‘Assign. dat/time’ and ‘Dates alloc’ in transaction /PACG/ECM_WBS - WBS (Service call) – Definition.
Dates alloc.
| Specify which dates should be used as service call start/end/due dates:
Specify which dates should be used as activity due/earliest start dates:
|
Assign. dat/time | Specify which dates from the activity WBS should be used as activity start date and end date:
|
DT order header | The related service call WBS’s basic date should be used as activity start/end date (if enabled, customizing in field ‘Assign. dat/time’ is not considered). |
Basic dates:
Forecast dates:
Default start/end time of activities
WBS elements cannot be assigned time, only dates. Use fields ‘Start of-’ and ‘End of Activity’ in transaction /PACG/ECM_SCTDF - WBS (Service call) - Default values to set default activity start/end time (during activity creation). Otherwise, activity time will be set as ’08:00:00 – 16:00:00’. This will be overwritten after dispatching the activity on the planning board in SAP FSM.
Duration
To create an activity with planned duration in minutes, change the duration unit to minutes in the project builder: