Network order integration has been designed with one of our customers in mind. In order to avoid misunderstandings or issues, we strongly recommend implementing it only with Proaxia’s Expert Support.

This is a project-spefic (PS integration) version of transaction /PACG/ECM_CKDET - Control key determination.

Define which control keys (in combination with network order types) are relevant for activity transfer to SAP FSM. Fist consideration is given to the setting which are responsible for definition of network definition (/pacg/ecm_sctdo).

Create AE

Customize if a new (copied in SAP FSM) activity should be assigned to the same operation as the source activity (option ‘N') or if a new operation should be created for this activity (option ‘Y’).

Update Act (S4) PACG 200 SP06

Allow to set up in which situation activity can be modified or it has blockade. There are 4 provided scenarios:

  • Allow activity element from SAP & FSM

  • Do not update activity from FSM

  • Do not update activity from SAP

  • Do not update activity from SAP & FSM

Res. cntr. key

If the field ‘Create AE’ is set to ‘Y', a new control key can be specified for the new operation.