Activity WBS elements with statuses other than I0043 (locked), I0045 (technically completed), I0046 (closed) or I0076 (deletion flag) can be updated in SAP ECC/S4 based on activity change in SAP FSM. The changes include person responsible role, basic/forecast dates, equipment and subject. 

Table of Contents

Person responsible

The technician assigned to an activity in SAP FSM will be added to activity WBS as partner role ‘VW Person responsible’.

Image Added

Equipment

Equipment added to an activity in SAP FSM will be added to activity WBS in SAP ECC/S4:

Image Added

 

Dates

Duration of inbound activities is added as activity WBS basic duration. Planned duration of inbound activities is added as activity WBS forecast duration.

Image Added

 

Activity start/end dates modified in SAP FSM affect both basic and forecast dates of corresponding activity WBSs.

Image Added

Example

The following two activity WBS elements are created. The first one has duration of 6 hours, the second 1 day.

Image Added

Image Added

Assign and release the activities in SAP FSM:

Image Added

Image Added

The dates, time and duration are updated in the dedicated FSM activity table:

Image Added

Basic and forecast dates are updated on the activity WBS element level.

Image Added

Image Added

 

Use field ‘No work/dur’ in transaction /PACG/ECM_WBS - WBS (Service call) - Definition to not update duration in activity WBS element based on duration and planned duration from SAP FSM.