Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Reserved materials can use project stock. FSM technicians can see not only unplanned project stocks but also the reserved materials from project stock.

 

Prerequisite

Make sure that a project stock is maintained as a special stock in transaction /PACG/ECM_WRHOUSE - FSM warehouse (field ‘WBS element’).

...

The stock should be transferred to FSM.

 

Process overview

A WBS element should be entered in service orders additional data:

...

If consumed on the mobile app, the following Goods movement is performed, with reference to the WBS element and special stock ‘Q’:

...

Prerequisite

Make sure that a project stock is maintained as a special stock in transaction /PACG/ECM_WRHOUSE - FSM warehouse.

...