(S4)PACG 200 SP04

Reserved materials can use project stock. FSM technicians can see not only unplanned project stocks but also the reserved materials from project stock.

 

Process overview

A WBS element should be entered in service orders additional data:

Create a stock item component:

 

The following reservation is created, with reference to the WBS element and special stock ‘Q’:

Project stock quantity is available for the test material:

The following reserved material IDoc is sent to FSM, using the project stock warehouse ('special stock'):

 

The reserved material can be found on the mobile (Android) app:

If consumed on the mobile app, the following Goods movement is performed, with reference to the WBS element and special stock ‘Q’:

Prerequisite

Make sure that a project stock is maintained as a special stock in transaction /PACG/ECM_WRHOUSE - FSM warehouse.

 