Service calls and activities in PP integration

Service calls and activities in PP integration

CREATION of service call/activities

Service Call transfer to FSM

PP orders can be created using the transaction CO01. Provide the material to be produced, production plant and order type.

image008.png

 

Only orders with quantity equal to 1 are relevant for FSM.

image009.png

 

Create routing and BOM for operations and components required for production planning.

image011.png

 

Operations overview:

image013.png

 

Components overview:

image015.png

 

Only production orders with serial number assigned are relevant for FSM.

image017.png

 

After the Production order is released and saved, a service call is automatically transferred to FSM.

image019.png

 

The service call can be found in the SAP FSM Planning and Dispatching by using the PP order number.

image023.png

 

Activity transfer to FSM

Activity will be transferred along with the service call IDoc (production order release and save).

image025.png
image027.png

Activities can be found in the activities tab of service call.

image029.png
image031.png

 

The activity can be dispatched to an available technician and then released. Activity release triggers transfer of this activity to SAP. The person responsible and start/end date and time is stored on activity level and can be displayed with transaction /PACG/ECM_ACTI_VC03 - Display FSM Activity:

image037.png
image039.png

 

HEADER material in PP integration

The material to be produced - indicated in the PP order header - can be transferred to FSM as a service product in the activity detail screen. 

image-20250219-084212.png

 

When the production order is released, the material to be produced is sent to FSM for all the operations in the PP order. 

image-20250219-084236.png

 

In FSM app, the technician can view the service product. 

image-20250219-084256.png
image-20250219-084306.png

 

DATE determination for Service call/activities

Service call start/end dates depend on the ‘Scall start/end and Act. earl.start/due’ setting of transaction /PACG/ECM_VPPSCTD - Prod order service call types def.. Either basic or scheduled dates can be used.

image043.png

Activity Planned dates depend on the ‘Activity planned start/end date’ setting of transaction /PACG/ECM_VPPSCTD - Prod order service call types def.. Earliest or latest dates of an operation can be used.

image046.png

 

ATTACHMENTS of Service call/activities

GOS/BDS/DMS attachments can be added to PP order and sent as service call and activity attachments to FSM.

Attachments added to service call and activity in FSM can be stored as GOS/BDS/DMS attachments in PP order.

 

From PP order to FSM Service call and activity

GOS: 

image048.png
image050.png

 

BDS:                                                                                                                                             

image052.png
image053.png

 

GOS and BDS attachment in FSM activity and service call:

image055.png
image057.png

 

From service call and activity to PP order.

GOS Attachment added in Activity and service call in FSM:

image061.png
image064.png

In PP order:

image065.png

 

BDS Attachment added to an activity in FSM

image069.png
image072.png

 

Related content