S/4HANA Service Order - Date fields mapping

S/4HANA Service Order - Date fields mapping

The Dates values in Service Order are stored on 2 levels: on Header level and Item level. The Header level corresponds to Service call and Item level reflect the Activity on FSM side. The Service Order has separate section with Dates value:

image-20240617-125511.png
Dates in the Service Order header in Fiori app

 

Service call - Service Order header

SAP => FSM

FSM Property

Source in SAP Fiori

FSM Property

Source in SAP Fiori

Planned start date

Planned date from has the highest priority. If this field is empty, then Requested start date is taken from Service Order.

Planned end date

Planned date to has the highest priority. If this field is empty, then Requested end date is taken from Service Order.

Earliest start date

Requested start date from Service Order

Due date

Requested end date from Service Order

FSM => SAP

FSM Property

Source in SAP Fiori

FSM Property

Source in SAP Fiori

Planned start date

Planned date from has the highest priority. If this field is empty, then Requested start date is taken from Service Order.

Planned end date

Planned date to has the highest priority. This date is passed to Requested end date if Due date in FSM is empty.

Earliest start date

Requested start date form Service Order

Due date

Requested end date from Service Order

Activity - Service Order Item

SAP => FSM

FSM Property

Source in SAP Fiori

FSM Property

Source in SAP Fiori

Planned start date

Planned date from has the highest priority. If this field is empty, then Requested start date is taken from Service Order Item. This date can be taken from header level, when this value is empty on item level.

Planned end date

Planned date to has the highest priority. If this field is empty, then Requested end date is taken from Service Order Item. This date can be taken from header level, when this value is empty on item level.

Planned Duration

Planned duration from Service Order Item

Estimated Duration

Quantity in HR units from Service Order Item

Earliest start date

Requested start date from Service Order Item

Due date

Due by from Service Order Item has the highest priority. If the field is empty, then Requested end date is taken from Item. If Requested end date on item level is empty, then the same date is taken from header service order level.

 

Related content

/PACG/ECM_VLOTD - S/4HANA Service Order types definition
/PACG/ECM_VLOTD - S/4HANA Service Order types definition
More like this
SAP S/4HANA Service Order - prerequisites and basic setup
SAP S/4HANA Service Order - prerequisites and basic setup
Read with this
Activity/service call dates mapping (SAP ⇿ FSM)
Activity/service call dates mapping (SAP ⇿ FSM)
More like this
S/4HANA Service Order - Reserved materials
S/4HANA Service Order - Reserved materials
Read with this
S/4HANA Service Order Arrival Date
S/4HANA Service Order Arrival Date